← /writing

Interconnection

Cluster 16 is mostly batteries: reading 62.6 GW of new requests

The preliminary CAISO queue for Cluster 16 holds 226 requests. More than four fifths of the capacity is standalone storage or solar paired with storage.

The California ISO posted the preliminary Cluster 16 queue report on October 16, 2026, the day after the application window closed. Requests in the report total 62.6 GW of net capacity at the point of interconnection.

Standalone storage leads at 28.9 GW, followed by solar with storage at 23.9 GW. Standalone solar adds 6.2 GW, and geothermal, wind, gas and other fuels together make up the remaining 3.6 GW.

Cluster 16 next to Cluster 15GW of net capacity at POI by technology. Cluster 15 counts the active and withdrawn sheets of the July 16, 2026 report.
CLUSTER 16CLUSTER 15
Storage
28.9
26.7
Solar + storage
23.9
23.2
Solar
6.2
6.1
Other
3.6
3.0

Where it wants to connect

PG&E territory draws the most requests at 85, followed by SCE with 64 and SDG&E with 33. GridLiance West and LS Power together account for another 37.

The busiest points of interconnection are Antelope 230 kV with 2,803 MW across 9 requests, Whirlwind 230 kV with 2,800 MW across 7, and Beatty 230 kV with 2,660 MW across 6. Manning 500 kV draws the most individual requests, 13, for 2,385 MW.

When it wants to come online

Requested commercial operation dates cluster between 2030 and 2033. The peak year is 2032 at 21.0 GW, with 14.5 GW in 2031 and 11.8 GW in each of 2030 and 2033. Only 1.3 GW asks for a date before 2030.

A caveat on the comparison

Cluster 15 figures come after the ISO's intake screening, so this compares a raw intake with a screened one. Scoring during the Customer Engagement Window, which runs to January 13, 2027, decides which Cluster 16 projects enter the study.